The gap between ambition and execution is stark. While regional governments targeted 53 gigawatts of new capacity, current projections suggest only 14.9 gigawatts will be operational by the decade's end. Project developers are struggling with financing constraints and a scarcity of gas turbines, which face lead times of at least five years. Only 11 gigawatts of the entire regional pipeline has secured the necessary hardware to proceed, leaving the majority of planned projects in limbo.
Vietnam faces the most significant shortfall, with only 3.7 gigawatts expected to come online against a 29.4 gigawatt target. Indonesia is similarly constrained, having secured turbines for just 200 megawatts of its 8.4 gigawatt pipeline, forcing the nation to lean back on coal to maintain grid stability. Singapore stands as the sole exception, with its turbine supply for all major projects already locked in.