The filing seeks a remand of the construction and operations plan, citing a need for the agency to reevaluate compliance with the Outer Continental Shelf Lands Act. While the Department of the Interior claims the move is a procedural necessity rather than a policy shift, critics argue it undermines the regulatory certainty required for large-scale energy investment. The 704-MW project, developed by the Danish energy firm Ørsted, is expected to supply electricity to 350,000 homes by the end of the year.
Legal challenges against the project, originally brought by the group Green Oceans, have previously faced judicial scrutiny. In January, U.S. District Court Judge Royce Lamberth ruled that government arguments regarding military radar interference were insufficient to stall progress on advanced developments. Despite this, the administration’s latest filing critiques the Bureau of Ocean Energy Management for failing to adequately account for competing interests like fishing and recreation.