Texas’s data center expansion is not clearly stopping, but its costs and constraints are becoming harder to ignore. A permit issued after the state resumed reviews appears to be for SpaceX’s proposed $24 billion Starbase project, while grid demand, housing pressure and opposition to new power lines are reshaping the debate.
The Texas Commission on Environmental Quality returned to normal permit reviews on Nov. 16, weeks before the Dec. 10 target for ERCOT’s audit reports. Gov. Greg Abbott had linked the pause to that review. In August, he effectively froze new grid connections for data centers; in September, he directed the agency to stop issuing air and other permits. A FracTracker and Public Citizen report said preliminary approvals for three gas-fired power projects intended to serve data centers had been mailed within days. Abbott press secretary Andrew Mahaleris said, “No permits have been approved.” Politico reported that the first permit after the review resumed appears to have gone to SpaceX for its Starbase project. The audit’s full findings are not public. ERCOT told the Public Utility Commission on Nov. 5 that 93% of companies had responded to its information requests.
A queue far larger than the grid’s current peak
ERCOT’s large-load queue totals 474 gigawatts—more than five times the grid’s record peak demand of just over 90 gigawatts. Public Utility Commission Chair Thomas Gleeson said in June that projections were extremely high and “a lot of that load will not actually come here.” ERCOT chief executive Pablo Vegas also said in April that the forecast exceeded the growth he expected. Senate Bill 6, signed last year, requires applicants to show they control a site, pay for most required grid upgrades, accept emergency disconnections and disclose duplicate Texas requests. The audit is intended to distinguish viable proposals from speculative ones; Gibson Dunn lists Dec. 10 as the target for ERCOT’s reports and Dec. 17 for a commission meeting.
Abilene shows both the scale of investment and the strain around it. Oracle told investors on Sept. 10 that six of the campus’s eight buildings had been delivered. Epoch AI translates that into 618 megawatts and estimates the final two buildings came online around Nov. 1, though Oracle has not confirmed that. Oracle representatives have cited 1,000 long-term jobs and about $30 million in annual city revenue after a tax abatement. The Texas Tribune estimated about 100 people would be needed to run the campus. Abilene sales tax revenue was 34% above the previous year through May, and Development Corporation of Abilene head Misty Mayo said new revenue is helping fund roads, downtown revitalization and schools.
The housing effects are also visible. Zillow figures put average Abilene rent near $2,600 a month, almost 50% higher in a year. Abilene Christian University said in June that more than 100 incoming students lacked fall housing. Michael Prado of the Abilene Hope Haven shelter said finding a home for a client, once a little over a month-long process, can now take up to six months; some callers are data center workers who lost their jobs and remained in town. Taylor County Judge Phil Crowley has also cited water restrictions negotiated for Stargate and thousands of housing units and RV spaces approved for new arrivals. He said counties cannot impose a data center moratorium without state permission.
West Texas’s energy landscape is changing alongside the buildout. Taylor County’s median asking land price is $10,825 an acre, more than double the statewide rural average, according to Land.com listings. AES is repowering its Buffalo Gap wind farm with about 60% fewer turbines while retaining maximum output of 526.5 megawatts; it expects the site back online in 2027 with 17 long-term jobs. Enbridge is building an 8,000-acre, $1.1 billion solar farm about 35 miles from Abilene after airspace conflicts with Dyess Air Force Base led it to switch from a wind plan. Gas has overtaken wind in the local generation queue for the first time since January 2016, the Texas Tribune reported. Researcher Joseph Rand said the “low-hanging fruit has been picked over” for wind, while UT professor David Spence said data centers’ need for round-the-clock power likely drew gas developers.
Transmission lines are another point of contention. West Texas average demand grew 12.3% in 2025, twice the statewide 6.1%, while congestion rose 27%, according to the commission’s market monitor, Potomac Economics. A 2023 law cut the commission’s review period for a line from 365 days to 180. After a House hearing, 30 representatives from both parties and Lt. Gov. Dan Patrick urged the commission to reject proposed lines. Utility trade group head Mark Bell said the process was insufficient for landowners facing lines of this length. Yet ERCOT warned in July that rolling blackouts were possible in the Permian Basin by summer 2027, and Texas Oil and Gas Association President Todd Staples described the region as relying on a “patchwork of portable generators.”
Some projects are designed to bypass the grid. Chevron has a 20-year agreement to supply Microsoft with 2.67 gigawatts of gas-fired power in Reeves County near Pecos, with electricity expected in 2028 and a final investment decision due by year-end. The plant would sit behind the meter. Waha, the Permian’s main gas hub, traded at negative prices on 118 of the first 131 trading days this year, meaning producers paid to dispose of gas. But there is no evidence Chevron’s project will capture flared gas; flaring intensity in the Permian fell nearly 10% from 2023 to 2024, largely as pipelines opened markets for gas. RBC Capital Markets counts about 38 gigawatts of announced behind-the-meter gas capacity in Texas, but several projects still lack customers.
The political timetable could bring new rules, though not immediately. Gina Hinojosa, elected governor on Nov. 3, promised to pause data center approvals until lawmakers pass protections. She told Fox’s Bret Baier she does not expect companies to leave Texas, saying, “I don’t hate data centers,” but objecting to how they are taking advantage of Texans. She takes office Jan. 19, after the Legislature convenes Jan. 12; the session ends May 31, and most legislation passed this spring would take effect Sept. 1, 2027. The incoming governor can appoint new chairs to the Public Utility Commission and environmental agency, with the possibility of appointing a majority of both commissions within her first year. BloombergNEF estimated Abbott’s grid-connection freeze alone could delay about 20% of the U.S. data center pipeline, and more if it continued into next year. The scale and duration of any new pause remain unknown.