The state's interconnection queue has ballooned in less than six months, with requests more than doubling since January. Data centers account for approximately 90% of these pending applications. While many are speculative paper proposals, the current volume represents over five times the total peak demand currently handled by the Electric Reliability Council of Texas.
Abbott is now demanding comprehensive disclosures from developers. The required data includes electricity and water consumption metrics, noise and light mitigation plans, ownership structures, and the utilization of tax incentives. This directive marks a sharp pivot for a state historically defined by its hands-off approach to industrial development. Previous attempts to gather this information via voluntary surveys largely failed, as most operators declined to participate.